(P-01)

For a new production line, the low-voltage infrastructure from the main distribution panel to machine feeds was built under a single responsibility.

Sector
Metal processing
City
Dilovasi / Kocaeli
Year
2025
Duration
18 days
Scope
12.000 m²
Measurable Result

Problem

With facility growth the existing distribution line had become insufficient; the new line's power infrastructure had to be built and commissioned without stopping production.

Result

The new line was energized ahead of the planned production schedule; acceptance measurements passed on the first attempt and no production loss occurred.

Scope of Work
  • Main distribution panel and 6 sub-panel installations
  • 1,900 m of cable tray and busbar line
  • Machine feed and grounding lines
  • Testing, measurement and commissioning reports
Products Used
  • LV distribution panels
  • NYY / N2XH cable groups
  • Cable carrying systems
  • Switchgear and protection equipment
Field Gallery
Panel Detail

The main panel has a 4,000 A busbar output with integrated compensation and power analyzer; sub-panels were labelled per line and delivered with measurement points.

Field Note

Installation proceeded zone by zone with isolation while production continued; connections requiring outages were scheduled into weekend planned stops.