(P-02)

Fixture layout in the high-bay warehouse was recalculated against lighting needs; the retrofit was completed without disrupting shift patterns.

Sector
Logistics / warehousing
City
Izmit / Kocaeli
Year
2024
Duration
12 days
Scope
22.000 m²
Measurable Result

Problem

With the old fixtures, aisle illuminance was below standard; maintenance costs were high and energy consumption strained the budget.

Result

Aisle illuminance was brought up to standard; measured consumption dropped by 38% and fixture maintenance intervals extended significantly.

Scope of Work
  • Lighting needs analysis and photometric calculation
  • Retrofit of 480 industrial LED fixtures
  • Aisle-based circuit and automation separation
  • Illuminance measurement and reporting
Products Used
  • Industrial LED fixtures
  • Lighting automation
  • Distribution and control panels
  • Cabling groups
Field Gallery
Panel Detail

Lighting feeds were separated per aisle; time- and occupancy-based automation was added to the control panel.

Field Note

Work was planned in night blocks around warehouse shifts; each block was handed over with a measurement report the next morning.