(P-02)
Fixture layout in the high-bay warehouse was recalculated against lighting needs; the retrofit was completed without disrupting shift patterns.
Problem
With the old fixtures, aisle illuminance was below standard; maintenance costs were high and energy consumption strained the budget.
Result
Aisle illuminance was brought up to standard; measured consumption dropped by 38% and fixture maintenance intervals extended significantly.
- Lighting needs analysis and photometric calculation
- Retrofit of 480 industrial LED fixtures
- Aisle-based circuit and automation separation
- Illuminance measurement and reporting
- Industrial LED fixtures
- Lighting automation
- Distribution and control panels
- Cabling groups


Field photo to be added
Field photo to be added
Field photo to be added
Field photo to be added
Panel Detail
Lighting feeds were separated per aisle; time- and occupancy-based automation was added to the control panel.
Field Note
Work was planned in night blocks around warehouse shifts; each block was handed over with a measurement report the next morning.